TRCN upgrades capacity, commissions 300MVA transformer in Abuja

Published

on

The Transmission Company of Nigeria (TCN) has commissioned a 300MVA transformer at its Katampe substation in Abuja.

The commissioning will increase electricity transmission capacity in the Federal Capital Territory, FCT and its environs.

Advertisements
NLNG

The new 300MVA 330/132kV transformer, commissioned on Sunday, raises the substation’s capacity from 450MVA to 750MVA, marking a significant upgrade in a bid to ensure stable electricity.

This means there is more electricity for the Abuja Electricity Distribution Company to offtake and distribute to homes, businesses and industries across Abuja and surrounding areas.

Advertisements

General Manager of TCN, Abuja region, Engr. Musa Shuaibu, speaking at thenocassion, noted that the project reflects TCN’s ongoing commitment to strengthening the national grid.

He noted that the additional capacity would support increased power delivery, improve grid stability and enhance electricity supply to key load centres.

“This installation underscores our resolve to continue expanding the transmission network to meet growing demand and improve service delivery,” Shuaibu said.

The project was executed under a collaborative initiative between TCN and the World Bank, aimed at rehabilitating and upgrading Nigeria’s transmission infrastructure.

The development comes amid broader efforts to address longstanding bottlenecks in the power sector, particularly constraints within the transmission segment that have often limited the evacuation of generated electricity.