TCN, AEDC lock in confusion over total ‘blackout’ in Kogi

Published

on

There may be no end to electricity blackout in Kogi State anytime soon as the Transmission Company of Nigeria and the Abuja Electricity Distribution Company are locked up in confusion over what was responsible for total black out in Kogi and other areas.

This is even as the TCN has vehemently opposed reasons abducted by the AEDC that some maintenance were ongoing at its Apo substation.

Advertisements
NLNG

AEDC had blamed scheduled maintenance of 100MVA power transformers at the Apo 132kV for electricity disruption in Kogi and listed Zango, Shetima, Apansede, Phase 1, Phase 2, and Crown Estate and environs as affected areas.

In swift response through a statement issued by the TCN Spokesperson, Ndidi Mbah, disagreed that no maintenance is being carried out as claimed by the AEDC.

Advertisements

“I like to clarify that no maintenance activity was carried out at our Apo 132kV Transmission Substation, contrary to the statement issued by AEDC.

According to TCN a maintenance had been carried out at its APO substation on 30th April 2026, when the transformer was taken offline in emergency due to arching observed on the transformer bushing.

“This means the power outage experienced by the DisCo’s customers in the areas listed in AEDC’s public announcement was not attributable to TCN,” TCN said.