The ₦59.457 billion Greater Dutse Water Supply Project: The fact behind the lies and Governor Namadi question

Published

on

Greater Dutse Water Project

BY Muhammad Bello Abdullahi

By October 2026, the Greater Dutse Water Supply Project is approaching the end of the 24-month completion period announced at its December 2024 flag-off. The central question for residents is no longer whether the project was launched, but how far construction has actually progressed.

Advertisements
NLNG

The Greater Dutse Water Supply Project has for years represented one of the most important unfinished infrastructure promises in Jigawa State. Conceived to address the chronic water shortage affecting Dutse and surrounding communities, the project was originally initiated decades ago but remained incomplete through successive administrations.

That changed publicly in December 2024 when the Federal Government formally revived the project and handed it over for construction.

Advertisements

The Federal Ministry of Water Resources and Sanitation said the project was valued at ₦59.457 billion and designed to address a daily water-supply deficit of about 10 million litres, serving more than 1.5 million people in Dutse and its environs. The announced completion period was 24 months.

That deadline makes the present moment particularly important.

NAMADI’S ROLE: ADVOCACY, NOT SOLE OWNERSHIP
Governor Umar Namadi’s administration has publicly associated itself with the revival of the project, but the available official records show that the Greater Dutse project is solely a Federal Government-funded project implemented through the Federal Ministry of Water Resources and Sanitation, rather than a project financed and executed exclusively by the Jigawa State Government.

In May 2024, however, Governor Namadi said his administration was working with the Federal Government on the project and disclosed that ₦5 billion had been allocated in connection with it.

The distinction matters.
A serious assessment of the governor’s performance should therefore examine two separate questions:
What has the Namadi administration done to facilitate the project?
What is the actual physical and financial status of the Federal project itself? Confusing the two could produce an inaccurate assessment.

FROM A 24-YEAR-OLD PROMISE TO A ₦59.4 BILLION PROJECT
The history of the Greater Dutse project makes the current situation even more significant.

Reports at the time of the 2024 flag-off described the project as having remained incomplete for approximately 24 years. The scheme was conceived during the administration of former Governor Saminu Turaki around 2000, with the objective of supplying approximately 10 million litres of water daily to Dutse and surrounding areas. For residents who have lived with water shortages for years, therefore, the December 2024 ceremony was not merely another government groundbreaking. It represented a renewed expectation that the long wait might finally be over.
But groundbreaking is not the same thing as completion.

THE TROUBLING QUESTION IN THE PUBLIC RECORDS
One of the most important pieces of evidence requiring scrutiny is the current project information published by Eyemark, a Nigerian public-project monitoring platform.

Its Greater Dutse Water Supply Project page, last modified 11 August 2026, describes the project as ongoing but records no contractor assigned, no amount released, no amount spent, no inspection date and no project activities on its publicly available monitoring page. It also lists an appropriation figure of about ₦41.98 million.

This information should not automatically be interpreted as proof that no work has occurred on the ground. Monitoring databases can be incomplete, delayed or dependent on information supplied through official channels.
But it raises a legitimate accountability question:
Why does a project publicly valued at ₦59.46 billion have such limited publicly verifiable implementation information?

That question deserves an official answer from the Federal Ministry of Water Resources, the contractor, the Jigawa State Government and other relevant agencies.

THE CLOCK IS NOW TICKING
The Federal Government’s December 2024 announcement said the project was expected to be completed within 24 months. That puts the expected completion period around December 2026.
As October 2026 approaches its end, only a short period remains before that announced deadline.
The critical issue, therefore, is not whether the project was commissioned or whether politicians attended its flag-off.
The real questions are: How many kilometres of pipeline have been completed? How much of the water-treatment infrastructure has been constructed? Have the proposed reservoirs been completed? What is the status of the intake and pumping infrastructure? How much money has actually been released? How much has been certified and paid?

Who is the contractor? What percentage of physical work has been completed?
When will residents actually receive water from the scheme? These are measurable questions, and they should be answered with documents rather than political statements.

Jigawa’s own planning documents recognise the project.
The importance of the project is also reflected in Jigawa State’s medium-term planning documents. The state’s 2025–2027 Water and Sanitation sector strategy specifically lists the Greater Dutse Water Supply Project among its programmes.

This demonstrates that the project is not peripheral to Jigawa’s water strategy. For Dutse, it is potentially transformative.
A functioning Greater Dutse water system could reduce dependence on private boreholes and water vendors, improve household water security and strengthen public-health outcomes. But infrastructure only becomes development when it is completed, commissioned and actually delivers the promised service.

The ₦59.4 billion question.
The size of the contract makes transparency particularly important.
The Federal Executive Council approved the Greater Dutse contract at approximately ₦59.457 billion in January 2025.

With such a substantial public investment, citizens should be able to follow the project from contract award to completion through a transparent implementation trail.
That trail should include:
the name and details of the contractor;
contract award documentation; commencement date; project milestones;
certified payments; percentage of physical completion; variations, if any;
revised completion date, if applicable;
independent inspection reports; and
commissioning and water-production tests. Without this information, public discussion inevitably becomes dominated by competing political narratives.

BEYOND POLITICS: DUTSE NEEDS WATER
The Greater Dutse project should not become another political football between the Federal Government and Jigawa State Government. The people of Dutse are less interested in who receives political credit than in whether water actually flows from their taps.

Governor Namadi can legitimately point to his administration’s collaboration with the Federal Government and its advocacy for the project’s revival. The Federal Government can equally point to the contract award and 2024 groundbreaking.

But ultimately, the project’s success should be measured in litres of potable water delivered to households—not in ceremonies, speeches or budget announcements.

Where does it stand?
Based on publicly available evidence reviewed for this article, the Greater Dutse Water Supply Project is officially still described as ongoing, and there is no reliable public evidence establishing that it has reached completion as of October 2026. The available monitoring information also does not provide enough verified detail to establish the project’s current physical percentage completion.

That does not prove that the project has stalled or been abandoned. It does, however, expose a serious public-information gap at precisely the moment when the project is approaching its announced 24-month completion window.
The Namadi administration, the Federal Ministry of Water Resources and Sanitation and the project contractor should therefore publish a joint, evidence-based status report.

Jigawa citizens deserve to know: How much has been spent? How much has been built? How much remains? And, most importantly, when will Greater Dutse finally have the water it was promised?
Until those questions are answered with verifiable evidence, the Greater Dutse Water Supply Project remains not just a water project—but a test of transparency, intergovernmental coordination and the ability of government to turn a decades-old promise into a functioning public service.